FEED starts and customer discussions advance
Front-end engineering began in August 2021. The Hyundai memorandum set a framework for future offtake, not realised product sales.
Arafura’s five-year financial record reflects the cost of advancing Nolans toward construction and the funding required to do so. FY2026 radically increased the cash and financial-asset base, but its large investing outflow was mainly a term-deposit transfer—not an equivalent amount spent building the mine.
Reading the figures: Units are stated above each table or beside the metric. Brackets denote negative amounts. Supported nil is shown as zero; unlike reporting bases remain separately labelled.
Separate from current financial assets.
Not presented as cash equivalents.
Includes expensed development costs.
Construction mobilisation followed; not production.
The early years funded engineering, front-end design and site enabling works, much of which was expensed rather than added to the exploration balance. The higher losses therefore cannot be read simply as worsening operating-mine margins: Nolans remained a development project.
Funding progressed through offtake agreements, conditional debt approvals and cornerstone equity commitments. The FY2026 report dates the board’s investment decision to May, while continuing to describe financial-close conditions and construction mobilisation separately from production.
Front-end engineering began in August 2021. The Hyundai memorandum set a framework for future offtake, not realised product sales.
The company completed FEED, commenced detailed design and enabling works, and signed binding Hyundai/Kia and Siemens Gamesa arrangements. Equity raising supported the programme.
Early works completion was followed by lower site activity while financing progressed. Final conditional debt approvals announced in July 2024 were after the June balance date.
Conditional senior debt commitments and a binding NRFC investment commitment advanced the funding plan. The later A$80m placement announcement was a subsequent event.
Hatch was appointed EPCM contractor in October 2025. The board took FID on 21 May 2026 and prepared for construction mobilisation; full operating production was not reported.
FY2026 financing transformed the balance sheet. Operating cash remained negative, while a large portion of funding was placed in term deposits. Cash equivalents and the separately classified current financial assets must remain distinct.
A$ million
AI-generated presentation · values from Five-year financial record through FY2026; no missing values plotted as zero.
A$ million
AI-generated presentation · values from Five-year financial record through FY2026; no missing values plotted as zero.
A$ million
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
| Net loss after tax | (35.558) | (96.380) | (100.974) | (19.242) | (41.086) |
| Operating cash flow | (27.164) | (69.402) | (109.042) | (34.918) | (19.538) |
| Investing cash flow | (3.908) | (4.054) | (3.819) | (2.743) | (509.663) |
| Financing cash flow | 44.964 | 177.562 | 26.354 | 22.676 | 725.262 |
| Closing cash and cash equivalents | 24.680 | 128.848 | 42.170 | 27.178 | 223.241 |
Years ended 30 June 2022-2026; A$ million. This is the latest five-year span in the existing extraction, not FY2021-FY2025.
FY2026 investing includes A$500.086m placed in term deposits; it must not be read as A$509.663m of mine construction spending.
FY2025 uses the later cash-flow comparative, which differs by A$1 in transaction costs and financing total from the earlier edition.
Source: Annual-report extractions; report editions are listed once in the consolidated source registry.
Removing the term-deposit placement from investing cash leaves approximately A$9.578m of other investing payments. This transparent calculation helps distinguish treasury allocation from exploration, PPE and security-deposit spending; it is not a new issuer-defined performance measure.
A$ million
| Metric | FY2026 |
|---|---|
| Closing cash and cash equivalents | 223.241 |
| Closing current financial assets | 500.000 |
| Cash transferred to term deposits during year | (500.086) |
| Other net investing cash, excluding term-deposit placement | (9.578) |
The first two rows are closing stocks; the last two are annual flows and cannot be added to the stocks.
The calculated A$9.578m other investing outflow includes PPE, exploration and security deposits. It is not a company-defined free-cash-flow measure.
The maturity and restriction details are not sufficient in the packet to label all current financial assets as immediately available cash.
Source: Annual-report extractions; report editions are listed once in the consolidated source registry.
Nolans FEED, detailed design, engineering and early works are treated as development activities outside the capitalised exploration scope. The FY2026 disclosure says development costs remain expensed until the bulk-earthworks contract is awarded. That accounting boundary is retained rather than forcing all project spending into one capex series.
A$ million
AI-generated presentation · values from Development expense and actual project payments; no missing values plotted as zero.
A$ million
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
| Project costs expensed | (28.175) | (85.593) | (77.899) | (18.272) | (33.937) |
| Project-cost payments within operating | (19.737) | (67.066) | (104.098) | (23.448) | (18.470) |
| Exploration payments within investing | (4.137) | (2.015) | (2.894) | (1.974) | (2.055) |
| PPE payments within investing | (0.160) | (0.279) | (0.124) | (1.033) | (7.447) |
Negative amounts are expenses or payments as labelled. Do not add project expense to project cash and call the sum total spending.
FEED, design and early-development costs were expensed; the capitalised exploration balance excludes those activities. Payment timing and accruals explain differences between expense and cash.
Source: Annual-report extractions; report editions are listed once in the consolidated source registry.
The expansion of total assets and equity is principally read alongside the cash raise and treasury assets, not as realised value from rare-earth production. The deferred exploration balance remains a separate book-cost measure.
A$ million
AI-generated presentation · values from Cash funding changed the balance sheet; no missing values plotted as zero.
A$ million
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
| Total assets | 143.322 | 259.532 | 170.090 | 155.852 | 867.672 |
| Total liabilities | 10.953 | 44.630 | 25.976 | 6.588 | 21.962 |
| Total equity | 132.368 | 214.902 | 144.114 | 149.264 | 845.710 |
| Deferred exploration and evaluation | 116.599 | 119.346 | 122.364 | 123.595 | 125.626 |
| Working capital | 14.692 | 89.376 | 20.085 | 24.344 | 712.260 |
FY2026 includes A$500m in current financial assets separately from cash equivalents. Working capital includes those financial assets and other current items; it is not all cash.
Deferred exploration is an accounting asset, not the market value of Nolans or a measure of all project spending.
Source: Annual-report extractions; report editions are listed once in the consolidated source registry.
Conditional project debt includes financing and completion-support facilities. Required equity, final documentation and other conditions can still affect drawdown. The reported absence of significant long-term borrowings does not convert conditional limits into cash.
The July 2026 settlement and share-purchase-plan amounts are subsequent events. They are not added to June cash or counted again in the FY2026 share-proceeds line.
A$ million
AI-generated presentation · values from Cash equity funding; no missing values plotted as zero.
A$ million
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
| Share proceeds before separately stated costs | 47.191 | 185.169 | 31.510 | 24.644 | 748.038 |
| Transaction costs paid | (1.988) | (6.693) | (1.578) | (1.437) | (22.505) |
The earlier extraction labels share proceeds “net”, but separate transaction-cost and lease rows reconcile to financing cash; the table retains the amount before those separate cash deductions.
Debt commitments, project-financing limits and later placement tranches are not cash equity proceeds.
Source: Annual-report extractions; report editions are listed once in the consolidated source registry.
The historical MMI grant cessation is mentioned in more than one extracted annual narrative. This report does not count the same A$15m as new income in both years or as new cash. It retains the extracted statutory total earnings without inventing a grant-adjusted measure.
FY2026 also includes A$7.999m of share-based expense versus A$1.051m in the comparative. Those awards affect earnings and equity but are not cash project payments.
Prepared solely from the existing year-by-year extraction datasets. No raw annual-report body, PDF, new database lookup or financial web research was used. Review is against those stored extractions, not a new independent original-document audit.
The source references in this report identify the public disclosures used and should be read with the associated section, table and reporting-period qualifications. This report paraphrases, organises and compares those disclosures for descriptive and educational purposes rather than reproducing source text.
Copyright and other rights in linked reports, company names, logos and third-party materials remain with their respective owners. MII Research does not claim affiliation with or endorsement by the company covered in this report, the ASX or cited organisations.
This report uses AI actively and extensively for evidence extraction, comparison, organisation, calculation checks, drafting, translation planning and presentation. Material claims received reasonable editorial review against cited public sources; this was not an audit, assurance engagement or independent verification. Limitations in public sources, AI systems and review may leave errors, omissions, inconsistencies or translation, classification and interpretation errors.
Any AI-generated visual accompanying this report must carry an adjacent, visible AI-generated label or caption. Such visuals are illustrative rather than source evidence and do not replace the cited annual-report text, table or section source.
This record is for general descriptive and educational information only. It is not financial-product, investment, legal, tax, technical or other professional advice; it is not a securities recommendation, valuation, target price, offer, solicitation or invitation to buy, sell or hold.
It does not consider any reader’s objectives, financial situation, needs, knowledge, experience or risk tolerance. Independently verify material information against the primary disclosures, obtain appropriate independent professional advice and do not use this record as the sole or primary basis for any decision.
Public sources are used in good faith, but no representation or warranty is made as to accuracy, completeness, reliability, currency or fitness for a particular purpose. To the maximum extent permitted by law, MII Research disclaims liability for direct, indirect, incidental, consequential, opportunity or investment loss arising from use of or reliance on this record; nothing excludes or limits liability that cannot lawfully be excluded or limited.
Report suspected errors to MII Research with the relevant report section and primary-source document and page reference so that the record can be reviewed and corrected where appropriate.